The Complete Guide to WIP Reporting for Contractors

By Martin · 15 min read · Updated 2026-02-02

After two decades helping contractors navigate the financial complexities of construction, I've seen the same pattern repeat itself: companies that master WIP reporting make better decisions, maintain healthier cash flow, and grow profitably. Those that don't often find themselves surprised by losses they should have seen coming months earlier.

This guide represents everything I wish every contractor understood about WIP reporting. Whether you're running your first WIP schedule or refining a process you've used for years, you'll find actionable insights to improve your financial management.

What Is a WIP Report?

A Work-in-Progress (WIP) report is the financial heartbeat of any construction company using percentage-of-completion accounting. It's a snapshot that shows the true profitability and billing status of every active project at a specific point in time.

Think of it this way: your bank balance tells you what cash you have today. Your WIP report tells you what profit you've actually earned and whether your billing is keeping pace with your work.

Why WIP Matters

Construction projects stretch across months or years, but you need to know how you're doing right now. The WIP report solves this fundamental problem by answering three critical questions:

  1. How profitable is each job, really? Not what you estimated at bid time, but based on current costs and realistic projections.
  2. Are we billing appropriately? Are you sitting on unbilled revenue (losing the use of your own cash), or have you billed ahead of your actual progress (creating a liability you'll have to work off)?
  3. What's our true financial position? Your P&L and balance sheet can't be accurate without proper WIP calculations.

Who Needs WIP Reporting?

If you use percentage-of-completion accounting (and most contractors with projects lasting more than a few months do), you need WIP reporting. This includes:

The exception is companies doing only very short-duration work (residential remodeling with jobs completed in days or weeks) who use completed-contract accounting. But even they benefit from understanding these principles for their longer projects.

Key Insight: Your WIP report is the single most important financial document you'll produce. It drives your revenue recognition, validates your balance sheet, and reveals problems while you still have time to fix them.

The Core WIP Calculation

At its heart, WIP reporting is about answering one question: "What percentage of this job have we completed?" Once you know that, everything else follows.

The Fundamental Formula

The most common method uses cost-to-cost percentage of completion:

% Complete = Costs to Date / Estimated Cost at Completion

Let's walk through a simple example:

% Complete = $225,000 / $450,000 = 50%

This job is 50% complete based on costs incurred.

From Percentage to Earned Revenue

Once you know the percentage complete, you can calculate earned revenue:

Earned Revenue = Contract Value × % Complete

In our example:

Earned Revenue = $500,000 × 50% = $250,000

You've earned the right to recognize $250,000 in revenue, regardless of what you've billed.

The Over/Under Billing Calculation

Now compare earned revenue to what you've actually invoiced:

Over/(Under) Billing = Billings to Date - Earned Revenue

If you've billed $280,000 on our example job:

Over/(Under) Billing = $280,000 - $250,000 = $30,000 Overbilled

You're $30,000 overbilled. This isn't revenue you've earned yet; it's a liability sitting on your balance sheet. You'll need to perform $30,000 worth of additional work before you can bill more.

Conversely, if you'd only billed $220,000:

Over/(Under) Billing = $220,000 - $250,000 = $(30,000) Underbilled

You're underbilled by $30,000. You've performed work you haven't yet invoiced. This is an asset—you have the right to bill this amount.

Gross Profit Recognition

The WIP calculation also determines your gross profit to date:

Gross Profit to Date = Earned Revenue - Costs to Date

In our example:

Gross Profit = $250,000 - $225,000 = $25,000

And your gross profit margin:

Gross Profit % = Gross Profit / Earned Revenue = $25,000 / $250,000 = 10%

Key Insight: The percentage-of-completion method recognizes profit as you perform work, not when you bill or collect payment. This matches revenue and costs in the same period, giving you a true picture of job profitability throughout the project lifecycle.

Anatomy of a WIP Schedule

Let's dissect a sample WIP schedule to understand every component. Here's a typical five-job WIP report:

Job Name Contract Value Costs to Date Est. Cost at Completion % Complete Earned Revenue Billings to Date Over/(Under)
Retail Plaza $1,250,000 $687,500 $1,000,000 68.8% $859,375 $875,000 $15,625
Medical Office $2,100,000 $1,575,000 $1,890,000 83.3% $1,750,000 $1,680,000 $(70,000)
Warehouse Exp $875,000 $196,000 $700,000 28.0% $245,000 $262,500 $17,500
Industrial Park $3,500,000 $1,050,000 $3,150,000 33.3% $1,166,667 $1,050,000 $(116,667)
Office Remodel $425,000 $382,500 $408,000 93.8% $398,500 $425,000 $26,500
TOTALS $8,150,000 $3,891,000 $7,148,000 54.4% $4,419,542 $4,292,500 $(127,042)

Let's walk through each column:

Job Name

Self-explanatory, but consistency matters. Use the same job names across all systems (accounting, project management, field reports).

Contract Value

The total amount you'll be paid if you complete the contract as specified. This includes:

Be conservative about including pending COs. If approval is uncertain, track them separately.

Costs to Date

All job costs incurred through the WIP date, including:

This should match your accounting system, but requires adjustments for:

Estimated Cost at Completion (EAC)

This is where the art meets the science. EAC is your best estimate of total job costs:

EAC = Costs to Date + Estimated Costs to Complete

For the Retail Plaza job:

EAC = $687,500 + $312,500 = $1,000,000

Your EAC drives everything else in the WIP calculation. If it's wrong, your profit recognition is wrong, your balance sheet is wrong, and your decision-making is compromised.

% Complete

Calculated as shown earlier: Costs to Date / EAC. In our table, the Retail Plaza is 68.8% complete ($687,500 / $1,000,000).

Notice the total portfolio is 54.4% complete overall—meaning you're slightly past the midpoint on your active work.

Earned Revenue

Contract Value × % Complete. For the Medical Office:

Earned Revenue = $2,100,000 × 83.3% = $1,750,000

This is revenue you have the right to recognize under percentage-of-completion accounting, regardless of billing status.

Billings to Date

The cumulative amount you've invoiced to the customer through the WIP date. This should tie directly to your accounts receivable and cash receipts records.

For the Warehouse Expansion: $262,500 billed against $245,000 earned means you're ahead of your billing schedule (overbilled).

Over/(Under) Billing

The critical balance sheet figure:

In our example, the portfolio shows net underbilling of $127,042. You have more than $127,000 in unbilled revenue sitting on your balance sheet—work completed but not yet invoiced.

Key Insight: Every line of your WIP schedule should be defensible. If you can't explain to a banker, surety, or auditor why your percentages and estimates are reasonable, you need better project tracking systems.

Reading Your WIP: What the Numbers Tell You

A WIP schedule isn't just a compliance exercise—it's a diagnostic tool that reveals the health of your business. Here's what to look for:

Margin Fade: The Silent Killer

Compare estimated gross profit percentage at different points in time. Let's examine the Medical Office job more closely:

At 25% Complete (Three Months Ago):

Today at 83.3% Complete:

The margin has eroded by 50%. Costs that weren't anticipated at bid time have appeared: scope creep, longer durations, rework, material cost increases not covered by escalation clauses.

This is margin fade, and it's one of the most common ways contractors lose money. The WIP report makes it visible early enough to respond—by negotiating change orders, cutting costs elsewhere, or at minimum, learning lessons for the next bid.

Overbilling Risk: Building Liabilities

Look at the Office Remodel:

This job is nearly done, but you've already billed everything. If the remaining 6.2% of work encounters problems—punchlist grows, final inspections reveal issues, owner disputes quality—you'll be performing work with no corresponding cash flow.

Chronic overbilling across your portfolio means you're constantly working off old billings rather than generating fresh cash. It's a treadmill that gets harder as you grow.

Underbilling: The Cash Flow Drain

The Industrial Park is 33.3% complete but underbilled by $116,667. You've performed nearly $120,000 in work you haven't invoiced yet. Why?

Common causes:

Whatever the cause, underbilling is your cash tied up in the field. On a $3.5 million project, every week of delay in billing costs you the use of substantial working capital.

The Jobs That Flipped

Keep historical WIP reports and compare. Has a job that was overbilled last month become underbilled? This "flip" often signals:

  1. You updated the EAC (recognized a loss), which increased earned revenue
  2. You're catching up on billing after being behind
  3. The project pace accelerated unexpectedly

Each scenario requires different management responses.

Portfolio-Level Metrics

Beyond individual jobs, look at aggregate ratios:

Total Over/Under Position: In our example, the portfolio is net underbilled by $127,042. This represents about 3.3% of earned revenue. Generally:

Average % Complete: At 54.4%, this portfolio is well-balanced. If you're consistently above 70% complete across most jobs, you're not booking enough new work. Below 30% suggests very early-stage jobs where estimates are least reliable.

Estimated Gross Profit:

Total Contract Value - Total EAC = $8,150,000 - $7,148,000 = $1,002,000
Portfolio GP% = $1,002,000 / $8,150,000 = 12.3%

This contractor is estimating 12.3% gross profit across the active portfolio. Compare this to your budget, historical performance, and industry benchmarks (typically 10-20% for most contractors).

Key Insight: Don't just file your WIP report away after producing it. Review it with your project managers, discuss every variance, update estimates based on current field conditions, and use the insights to inform bidding, project management, and cash planning.

Percentage of Completion Methods

While cost-to-cost is the most common method, it's not the only approach. Understanding the alternatives helps you choose the right method for each project.

Cost-to-Cost Method

Formula: Costs to Date / Estimated Cost at Completion

Best for: Most construction projects where costs correlate reasonably with work progress.

Advantages:

Limitations:

Example: A $1M project with $400K spent and $800K estimated total cost is 50% complete ($400K / $800K).

Units of Delivery Method

Formula: Units Completed / Total Units to Complete

Best for: Projects with clearly measurable units: linear feet of pipe, cubic yards of concrete, square feet of paving, number of units.

Advantages:

Limitations:

Example: A pipeline project with 12,500 linear feet installed of 25,000 total is 50% complete (12,500 / 25,000).

Engineering/Architect Estimates Method

Formula: Based on periodic assessments by engineers or architects

Best for: Complex projects where neither costs nor units reflect true progress, such as industrial facilities, specialized systems, or design-build.

Advantages:

Limitations:

Example: An engineer certifies that a wastewater treatment plant is 60% complete based on inspection of systems, even though costs suggest 55%.

Choosing the Right Method

Most contractors use cost-to-cost as the default and adjust for special circumstances:

  1. Front-loaded projects: If mobilization or material purchases represent 30% of costs but only 10% of work, consider:

    • Excluding mobilization from the percentage calculation
    • Using units method for the physical work
    • Making manual adjustments to percentage based on engineering judgment
  2. T&M work: Cost-to-cost doesn't apply when the customer pays actual costs plus markup. Recognize revenue as costs are incurred (essentially 100% complete at all times for WIP purposes).

  3. Lump sum with minimal cost tracking: If you don't have reliable job costing, engineering estimates may be your only option—but this reveals a more fundamental problem you need to solve.

  4. Mixed contracts: Use different methods for different components. A job might be 40% complete on the base building (cost-to-cost) and 60% complete on the MEP rough-in (units method).

Key Insight: The method you choose must reasonably reflect actual project progress. Consistency matters—don't change methods mid-project without good reason and proper documentation. Your auditor will ask why, and you need a defensible answer.

Common WIP Mistakes

After reviewing hundreds of WIP schedules over my career, I see the same mistakes repeatedly. Avoid these pitfalls:

Not Updating Estimated Cost at Completion

The single biggest error. Contractors leave EAC at the original budget for months, even as reality diverges. Meanwhile, costs accumulate, percentages climb, and profit recognition becomes fiction.

The Fix: Update EAC monthly, informed by:

If your job is 40% complete but you've already spent 50% of the budget, your EAC needs adjustment. Don't wait until it's "certain"—make your best estimate now and refine it next month.

Ignoring Pending Change Orders

You've submitted $50,000 in change orders. The owner hasn't approved them, but you're confident they will. So you include the $50,000 in contract value. Then:

  1. The owner approves only $30,000
  2. Your earned revenue drops
  3. Your gross profit takes an unexpected hit
  4. Your auditor questions your aggressive recognition

The Fix: Conservative contract value. Only include COs that are:

Track pending COs separately in your WIP notes. They're relevant context, but don't count them as revenue until they're solid.

Annual-Only WIP

Some contractors produce WIP reports only at year-end for their CPA. This is financial management malpractice.

Problems you can't see until too late:

The Fix: Monthly WIP at minimum. Weekly for jobs over $1M or those with thin margins. The cost of producing frequent WIP reports is trivial compared to the cost of discovering problems late.

PM Estimates Disconnected from Reality

Your PM says the job is "about 60% done" based on feeling, but costs say 45%. You use 60% because the PM is closer to the work. Then at 90% complete, you discover significant rework is needed. The job was never at 60%.

The Fix: Use cost-to-cost as the default and make adjustments only with specific, documented justification. PMs are optimists (it's why they're good at their jobs), but WIP requires objectivity.

Not Reconciling Billings

Your WIP says $500,000 billed; your accounting system says $485,000. Which is right? If you don't reconcile, your balance sheet is wrong.

The Fix: Billings to Date on WIP must tie exactly to:

AR Beginning Balance + Revenue Recognized - Cash Receipts = AR Ending Balance

This should be automatic if you're pulling from accounting software. If you're using spreadsheets, reconcile monthly.

Forgetting About Retainage

Many contractors net retainage out of billings, but the proper WIP treatment is:

If you're netting retainage from billings, your over/under calculation will be wrong.

Poor Documentation

You can't defend your WIP estimates if you don't document the basis. When your surety underwriter asks why the EAC increased by $200,000, "it just did" isn't an acceptable answer.

The Fix: Maintain WIP notes for each job:

This documentation becomes critical during audits, surety renewals, and loan applications.

Key Insight: Most WIP mistakes stem from one root cause: treating WIP as a compliance task rather than a management tool. When you use WIP to actively manage projects, the quality and accuracy improve naturally because you need good data to make good decisions.

How Often to Run WIP

The frequency of WIP reporting should match the pace and risk profile of your business.

Monthly Minimum

This is the standard for most contractors with projects over 90 days. Monthly WIP allows you to:

Process:

This cadence makes year-end closing trivial because you've been maintaining WIP accuracy all year.

Weekly for At-Risk Jobs

Some projects demand more frequent monitoring:

Weekly WIP on these projects is less formal—often a PM estimate review meeting with accounting checking cost accumulation rates. You're watching for trend changes that require immediate action.

Daily for Crisis Management

I've helped contractors implement daily WIP monitoring when:

This is temporary intensive care, not sustainable long-term practice. But when needed, it can mean the difference between controlling a crisis and being controlled by it.

Quarterly Is Not Enough

Some contractors produce WIP only quarterly, aligned with bank reporting. This is inadequate because:

If banking requirements drive quarterly WIP, produce it monthly internally and provide quarterly packages to the bank.

Balancing Cost and Value

"But monthly WIP takes so much time!" I hear this often. The reality:

Manual spreadsheet WIP: 2-4 hours per month per person (accounting + PM input) Automated WIP system: 30-60 minutes per month

Even at the high end, 8 hours per month to know the financial truth about a $10M portfolio is one of the best investments you can make.

Key Insight: The frequency of WIP reporting sends a message about what you value. Monthly WIP says "we manage our business with current information." Quarterly or annual WIP says "we produce financial reports because we have to." Which company would you rather own?

WIP and Your Stakeholders

Your WIP schedule serves multiple audiences, each with different interests and concerns.

What Banks Want to See

Your lender cares about two things:

  1. Collectibility: Are you billing in line with progress? Significant underbilling suggests cash flow pressure. Significant overbilling suggests you're working off old billings and may face a cash crunch when those jobs complete.

  2. Profitability: Is your portfolio making money? Banks monitor estimated GP percentage because it indicates whether you'll generate enough cash flow to service debt.

Red flags from a banker's perspective:

What to provide:

Many loan covenants include WIP-based metrics. Know your covenants and monitor compliance monthly, not just when the quarterly package is due.

What Sureties Care About

Your bonding company underwrites risk based on your backlog relative to your capacity. WIP reporting is critical because:

  1. Work-on-hand calculation: Your bonded backlog isn't just signed contracts; it's contracts minus earned revenue. The surety needs accurate WIP to know your remaining bonded work.

  2. Profitability trends: A surety wants to see consistent, reasonable margins. They'll reduce your bonding capacity if jobs consistently erode from bid margins.

  3. Over/under billing positions: Extreme positions (net overbilling over 20% or net underbilling over 20%) suggest either cash flow stress or billing relationship problems.

Red flags from a surety perspective:

What to provide:

Many sureties now require monthly or quarterly WIP submissions, not just annual. The surety bond is your ticket to larger projects—maintain the relationship with transparent, accurate reporting.

What Your CPA Needs for Year-End

If you maintain monthly WIP all year, year-end is straightforward. Your CPA needs:

The CPA's job is to audit or review your WIP and ensure it's prepared in accordance with GAAP. They're looking for:

Reasonable estimates: Can you support your EAC figures with detailed cost analysis?

Consistency: Have you applied the same percentage-of-completion method consistently across jobs and periods?

Collectibility: Is the contract value realizable? Are there disputes or customer financial issues?

Proper cutoff: Do costs to date match the report date? (No early or late cost inclusion)

Documentation: Can you recreate how you arrived at each figure?

Many accounting firms charge less for audit work when clients maintain strong monthly WIP processes. You've done 90% of their work already, so they're not starting from scratch at year-end.

Internal Stakeholders: PMs and Owners

Beyond external reporting, WIP serves internal management:

Project Managers need WIP data to:

Ownership needs WIP to:

Regular WIP review meetings—monthly with PMs present—create accountability and improve estimate accuracy. When PMs know their estimates will be reviewed and questioned, they get more rigorous about updating them.

Key Insight: Think of your WIP schedule as a communication tool, not just a report. Different audiences need different presentations of the same underlying data. Customize your delivery for each stakeholder while maintaining one single source of truth.

From Manual to Automated

The evolution of WIP reporting capability often mirrors the evolution of a construction company. Understanding this progression helps you know what's next for your business.

Stage 1: The Spreadsheet

Most contractors start here:

Pros: Low cost, maximum flexibility, complete control

Cons: Error-prone, not scalable, no audit trail, time-intensive

Appropriate for: Very small contractors (under $5M revenue), companies with only 2-3 active jobs

Stage 2: Accounting Software WIP

As you grow, you move WIP into your accounting system:

Pros: Integration with accounting, reduced errors, better audit trail

Cons: Rigid structure, limited reporting flexibility, still requires manual PM input for estimates, often clunky interfaces

Appropriate for: Companies from $5M-$50M revenue with established accounting practices

Stage 3: Purpose-Built WIP Tools

Modern WIP platforms integrate with accounting but add specialized functionality:

Pros: Optimized for WIP workflow, better PM engagement, sophisticated analysis, modern interface

Cons: Additional cost, integration requirements, change management

Appropriate for: Companies serious about financial management, those with 10+ concurrent jobs, firms seeking to scale

This is where tools like ChainLink CFO fit—built specifically to solve the WIP reporting challenge with modern technology.

Stage 4: Fully Integrated Construction Management

Enterprise contractors eventually integrate WIP into broader construction management platforms:

Pros: Single source of truth, real-time data, comprehensive analytics

Cons: Expensive, complex implementation, requires dedicated systems personnel

Appropriate for: Large contractors ($100M+), those with IT resources

Making the Transition

Each stage transition requires change management:

Spreadsheet to Accounting Software:

Accounting Software to Purpose-Built Tools:

The Common Thread: Regardless of system sophistication, the quality of your WIP output depends on:

  1. Accurate, timely job costing
  2. Honest, detailed PM estimates
  3. Consistent monthly processes
  4. Management commitment to using WIP data for decisions

No software fixes bad processes. But good processes become dramatically more efficient with the right tools.

What to Automate First

If you're still heavily manual, prioritize automation in this order:

  1. Job cost data integration: Eliminate manual entry of costs to date
  2. Contract value tracking: Automatic pulling of original contract + approved COs
  3. Basic percentage calculations: Let software calculate % complete, earned revenue, over/under
  4. Comparison reporting: Automated month-over-month variance analysis
  5. PM estimate workflow: Digital forms and approvals
  6. Advanced analytics: Margin fade alerts, cash flow projections, capacity planning

Each step reduces time spent on data entry and calculation, freeing you to focus on analysis and decision-making.

Key Insight: The goal isn't automation for its own sake—it's to free your brain from manual calculation so you can focus on the questions that matter: Why is this job losing money? How do we fix it? Should we bid this next opportunity? That's where CFO-level thinking makes the difference.

Key Takeaways

After 3,000+ words on WIP reporting, here's what matters most:

  1. WIP is your financial heartbeat. It's not a compliance burden—it's the tool that lets you manage construction profitability proactively rather than discover problems in retrospect.

  2. The percentage-of-completion calculation is simple; the estimate quality is hard. Your WIP is only as good as your estimated costs at completion. Invest in accurate, updated PM estimates.

  3. Read your WIP, don't just produce it. Look for margin fade, dangerous over/under positions, and jobs that have flipped. Every variance tells a story.

  4. Monthly is the minimum. Quarterly WIP is financial negligence. You can't manage what you only measure four times a year.

  5. Different methods for different projects. Cost-to-cost is the standard, but units method or engineering estimates may be more appropriate for specific job types.

  6. Avoid the common mistakes. Update your EAC monthly, be conservative with pending COs, reconcile your billings, and document everything.

  7. WIP serves multiple masters. Your bank, surety, CPA, and internal team all need WIP data, each with different priorities. Know what each stakeholder cares about.

  8. Progress from manual to automated thoughtfully. Every growing contractor eventually hits the limits of spreadsheet WIP. Know the stages and plan your evolution.

  9. Over/under billing positions matter. Chronic overbilling builds liabilities you'll work off without cash. Heavy underbilling ties up your working capital. Balance is health.

  10. WIP enables strategic thinking. When you know job profitability in real-time, you can make better decisions about bidding, staffing, growth, and risk management. This is the foundation of CFO-level construction finance.

Your WIP report should be the first document you review every month and the foundation of every strategic conversation. Master WIP reporting, and you've mastered the single most important aspect of construction financial management.

When you're ready to move beyond spreadsheets to a purpose-built WIP solution, ChainLink CFO is designed to make everything in this guide easier, faster, and more accurate. But the principles remain the same regardless of your tools—accurate estimates, timely reporting, honest analysis, and management action based on what the numbers tell you.

That's what separates contractors who grow profitably from those who simply get bigger until they collapse under the weight of jobs they didn't know were losing money.